2008年6月ACCA考试:Part I真题答案(1)

更新时间:2020-01-16 14:11:43 来源: 阅读量:

【摘要】 关注ACCA考试历年真题可以更好地掌握考试出题动向,明确知识点和考查方式。考必过小编为大家精心整理了2008年6月ACCA考试:Part I真题答案(1),希望能够帮助即将参加ACCA考试的考生们顺利达成考试目标。让我们来看看2008年6月ACCA考试:Part I真题答案(1)的详细内容吧,内容如下:

2008年6月ACCA考试:Part I真题答案(1)

导读:无忧考网提供了“2008年6月ACCA考试:Part I真题答案“希望对后来者有所启示。  1 (a)(i)Stakeholders  A stakeholder can be defined as any person or group that can affect or be affected by an entity. In this case, stakeholders are those that can affect or be affected by the building of the Giant Dam Project. Stakeholding is thus bi-directional. Stakeholders can be those (voluntarily or involuntarily) affected by the activities of an organisation or the stakeholder may be seeking to influence the organisation in some way.  All stakeholding is characterised by the making of ‘claims’ upon an organisation. Put simply,stakeholders ‘want something’ although in some cases, the ‘want’ may not be known by the stakeholder (such as future generations).It is the task of management to decide on the strengths of each stakeholder’s claim in formulating strategy and in making decisions. In most situations it is likely that some stakeholder claims will be privileged over others.  R&M’s external stakeholders include:  - The client (the government of the East Asian country)  - Stop-the-dam pressure group  - First Nation (the indigenous people group)  - The banks that will be financing R&M*s initial working capital  - Shareholders  (ii) Stakeholder claims  Four external stakeholders in the case and their claims are as follows.  The client,i.e. the government of the East Asian country. This stakeholder wants the project completed to budget and on time. It may also be concerned to minimise negative publicity in respect of the construction of the dam and the possible negative environmental consequences.  Stop-the-dam,the vocal and well organised pressure group. This stakeholder wants the project stopped completely,seemingly and slightly paradoxically,for environmental and social footprint reasons.  First Nation,the indigenous people group currently resident on the land behind the dam that would be flooded after its construction. This stakeholder also wants the project stopped so they can continue to live on and farm the land.  The banks (identified as a single group). These seem happy to lend to the project and will want it to proceed so they make a return on their loans commensurate with the risk of the loan. They do not want to be publicly identified as being associated with the Giant Dam Project.  Shareholders. The shareholders have the right to have their investment in the company managed in such a way as to maximise the value of their shareholding. The shareholders seek projects providing positive NPVs within the normal constraints of sound risk management.  Tutorial note:only four stakeholders need to be identified. Marks will be given for up to four relevant stakeholders only.

以上就是2008年6月ACCA考试:Part I真题答案(1)的详细内容,生命需要保持一种激情,相信奋斗以后一定会有好的成果,小编整理的资讯内容希望能够帮助即将参加ACCA考试的考生们顺利达成考试目标,加油。更多资讯关注考必过网站,最新消息小编会第一时间发布!

分享到: 编辑:admin

考试真题关键词